Utility
Ashtabula II - Luverne
Substation & Transmission
Project
Description
CEG designed the Phase I Collection System (North, 50 MW), the 150 MW 34.5KV to 230KV step up substation and the 11.5 mile 230KV transmission line for this M-Power/Otter Tail/ Minnkota project.
Description Box Description Box